Session aimPower supplies commissioning and Cu-nD irradiation
Session day2006-12-18Operatorpduarte
Session IDISTTOK_20061218_1Coordinatorhf

Shot Time Operator Iplasma(kA) n(1018m-3) Duration (ms) Pre/post shot comments
137532006-12-18 18:47:06.74pduarte000only PRECO
137522006-12-18 18:41:52.195pduarte000only PRECO. ELCO failure.
137512006-12-18 18:36:40.303pduarte000only PRECO
137502006-12-18 18:30:54.143pduarte000only PRECO
137492006-12-18 18:25:20.286pduarte000only PRECO
137482006-12-18 18:17:27.335pduarte1.92.831PI feedback on Horizontal field till 30 ms and P feedback on Vertical field from 3 till 30 ms. ELCO=150V
137472006-12-18 18:11:26.473pduarte1.62.631PI feedback on Horizontal field till 30 ms and P feedback on Vertical field from 3 till 30 ms. ELCO=150V
137462006-12-18 18:05:43.238pduarte1.72.431PI feedback on Horizontal field till 30 ms and P feedback on Vertical field from 3 till 30 ms. ELCO=150V
137452006-12-18 18:00:19.766pduarte1.52.331PI feedback on Horizontal field till 30 ms and P feedback on Vertical field from 3 till 30 ms. ELCO=150V
137442006-12-18 17:54:16.178pduarte22.231PI feedback on Horizontal field till 30 ms and P feedback on Vertical field from 3 till 30 ms. ELCO = 150V
137432006-12-18 17:47:53.867pduarte1.62.131PI feedback on Horizontal field till 30 ms and P feedback on Vertical field from 3 till 30 ms
137422006-12-18 17:41:20.381pduarte000only PRECO. Without power supplies.
137412006-12-18 17:35:45.077pduarte1.62.131PI feedback on Horizontal field till 30 ms and P feedback on Vertical field from 3 till 30 ms
137402006-12-18 17:30:06.788pduarte1.21.931PI feedback on Horizontal field till 30 ms and P feedback on Vertical field from 3ms till 30 ms
137392006-12-18 17:23:32.887pduarte1.82.113PI feedback on Horizontal field till 30 ms and P feedback on Vertical field from 10ms till 20 ms
137382006-12-18 17:16:42.26pduarte005only PRECO. PI feedback on Horizontal field till 30 ms and P feedback on Vertical field till 20 ms
137372006-12-18 17:09:55.242pduarte1.5131PI feedback on Horizontal field till 30 ms and P feedback on Vertical field till 20 ms
137362006-12-18 17:03:47.29pduarte2.51.915PI feedback on Horizontal field till 30 ms and P feedback on Vertical field till 20 ms
137352006-12-18 16:55:58.368pduarte1.31.231PI feedback test on Horizontal field till 30 ms
137342006-12-18 16:47:02.986pduarte1.91.831PI feedback test on Horizontal field till 30 ms
137332006-12-18 16:41:22.354pduarte1.41.422PI feedback test on Horizontal field till 30 ms
137322006-12-18 16:32:24.748pduarte1.41.231PI feedback test on Horizontal field till 30 ms
137312006-12-18 16:26:57.997pduarte1.71.830PI feedback test on Horizontal field till 30 ms
137302006-12-18 16:20:50.13pduarte1.31.431PI feedback test on Horizontal field till 30 ms
137292006-12-18 16:08:06.013pduarte1.31.331P feedback test on Horizontal field till 30 ms
137282006-12-18 15:59:08.149pduarte1.11.622P feedback test on Horizontal field till 20 ms
137272006-12-18 15:53:09.934pduarte1.51.626P feedback on Horizontal field till 20 ms
137262006-12-18 15:44:25.118pduarte000only PRECO. ELCO failure.
137252006-12-18 15:39:00.269pduarte000only PRECO. Feedback test.
137242006-12-18 15:31:12.374pduarte1.31.630Horizontal field on
137232006-12-18 15:24:10.759pduarte1.11.625Horizontal field on.
137222006-12-18 15:15:17.504pduarte1.11.530Horizontal field on
137212006-12-18 15:09:58.588pduarte005only PRECO. Feedback debug. Feedback test on Horizontal field.
137202006-12-18 15:04:07.445pduarte005only PRECO. Feedback debug. Feedback test on Horizontal field.
137192006-12-18 14:55:27.713pduarte000Software shot. Feedback debug. PID test.
137182006-12-18 14:48:50.202pduarte000Software shot. Feedback debug. PID test.
137172006-12-18 14:43:46.586pduarte000Software shot. Feedback debug.
137162006-12-18 14:27:43.536pduarte000software shot on Manual Clean. Feedback debug.
137152006-12-18 14:12:25.399pduarte000only PRECO.
137142006-12-18 14:07:10.735pduarte000only PRECO. Cu-nD at position r=60mm.
137132006-12-18 14:00:40.72pduarte000only PRECO. Cu-nD at position r=60mm.
137122006-12-18 13:55:01.739pduarte000only PRECO. Horizontal field on. Cu-nD at position r=60mm.
137112006-12-18 13:48:26.778pduarte000only PRECO. ELCO failure.
137102006-12-18 13:38:55.209pduarte000only PRECO. ELCO failure
137092006-12-18 13:33:38.483pduarte000gas failure