Session aimZeff and new poloidal rake commissioning
Session day2007-01-25Operatorpduarte
Session IDISTTOK_2007125_1Coordinatorcsilva

Shot Time Operator Iplasma(kA) n(1018m-3) Duration (ms) Pre/post shot comments
140622007-01-25 17:49:32.883pduarte000Power supplies controler failure
140612007-01-25 17:31:29.292pduarte2.92.515PI Feedback on Vertical field and pre-programed Horizontal field. AC
140602007-01-25 17:21:15.232pduarte2.82.515PI Feedback on Vertical field and pre-programed Horizontal field. AC
140592007-01-25 17:11:35.102pduarte2.42.515Pre-programed Horizontal field. AC
140582007-01-25 17:03:11.944pduarte2.52.515Pre-programed Horizontal field. AC
140572007-01-25 16:46:28.11pduarte2.5315PID Feedback on Vertical field and pre-programed Horizontal field. AC
140562007-01-25 16:35:32.486pduarte32.515PID Feedback on Vertical field and pre-programed Horizontal field. AC
140552007-01-25 16:24:50.714pduarte2.82.820PID Feedback on Vertical field and pre-programed Horizontal field.
140542007-01-25 16:05:16.178pduarte2.82.825PID Feedback on Vertical field and pre-programed Horizontal field.
140532007-01-25 15:53:22.215pduarte2.72.725PID Feedback on Vertical field and pre-programed Horizontal field.
140522007-01-25 15:46:56.828pduarte22.725PI Feedback on Vertical field and pre-programed Horizontal field.
140512007-01-25 15:35:24.245pduarte1.72.725PI Feedback on Vertical field and pre-programed Horizontal field.
140502007-01-25 15:26:11.353pduarte1.52.725Feedback on Horizontal field and on Vertical field.
140492007-01-25 15:16:06.296pduarte1.42.725Feedback on Horizontal field and on Vertical field.
140482007-01-25 15:05:35.46pduarte1.22.625Feedback on Horizontal field and on Vertical field.
140472007-01-25 14:46:04.916pduarte000Power supplies controler failure.
140462007-01-25 14:26:24.15pduarte000The radial rake probes have been replaced by poloidal rake probes. Power supplies controler failure.