Session aimIon beam measurements
Session day2007-02-06Operatorpduarte
Session IDISTTOK_200726_2Coordinatorcsilva

Shot Time Operator Iplasma(kA) n(1018m-3) Duration (ms) Pre/post shot comments
141642007-02-06 16:18:10.352pduarte5225P Feedback on Horizontal fiel and 2 ms period comb on Vertical field. Primary Resistor = 0,25 ohms
141632007-02-06 16:12:48.359pduarte4.52.525P Feedback on Horizontal fiel and on Vertical field.
141622007-02-06 16:07:10.865pduarte4.52.420P Feedback on Horizontal fiel and pre-programed Vertical field.
141612007-02-06 16:00:03.117pduarte4.12.525P Feedback on Horizontal fiel and on Vertical field. Horizontal position setpoint=-10mm
141602007-02-06 15:52:43.147pduarte4.3025P Feedback on Horizontal fiel and on Vertical field.
141592007-02-06 15:46:08.488pduarte4.32.525P Feedback on Horizontal fiel and on Vertical field.
141582007-02-06 15:40:36.328pduarte4.52.525Feedback on Horizontal field.
141572007-02-06 15:35:11.808pduarte4.7225P Feedback on Horizontal field.
141562007-02-06 15:28:10.299pduarte4.52.225Feedback on Horizontal and on Vertical power supply.
141552007-02-06 15:19:00.935pduarte52.520Feedback on Horizontal and on Vertical power supply.
141542007-02-06 15:13:39.616pduarte4.12.525Feedback on Horizontal and on Vertical power supply.
141532007-02-06 15:08:21.767pduarte3.51.810Feedback on Horizontal and on Vertical power supply.
141522007-02-06 15:02:11.964pduarte4.12.625Feedback on Horizontal and on Vertical power supply.
141512007-02-06 14:56:21.847pduarte3.52.215Feedback on Horizontal and on Vertical power supply.
141502007-02-06 14:50:19.266pduarte42.315Feedback on Horizontal and on Vertical power supply.
141492007-02-06 14:42:25.895pduarte000Power supplies failure
141482007-02-06 14:34:35.531pduarte3.52.510Pre-programed Horizontal field and feedback on Vertical field.
141472007-02-06 14:27:22.664pduarte3.22.28Pre-programed Horizontal field and feedback on Vertical field.
141462007-02-06 14:20:41.304pduarte000Power suppplies failure