Session aimPosition tests
Session day2007-02-07Operatorpduarte
Session IDISTTOK_200727_2Coordinatorcsilva

Shot Time Operator Iplasma(kA) n(1018m-3) Duration (ms) Pre/post shot comments
142002007-02-07 17:54:08.695pduarte42.327P feedback on Horizontal field and pre-programed step on Vertical field. Vertical position setpoint = 8mm.
141992007-02-07 17:47:16.501pduarte4.22.427P feedback on Horizontal field and pre-programed step on Vertical field.
141982007-02-07 17:39:55.334pduarte4.22.327P feedback on Horizontal field and pre-programed 2 step on Vertical field. Vertical position setpoint = -10mm.
141972007-02-07 17:34:14.319pduarte4.82.515P feedback on Horizontal field and pre-programed 2 step on Vertical field. Vertical position setpoint = -10mm.
141962007-02-07 17:26:36.579pduarte4.82.515P feedback on Horizontal field and pre-programed 2 step on Vertical field. Vertical position setpoint = -10mm.
141952007-02-07 17:19:47.555pduarte52.518P feedback on Horizontal field and pre-programed 2 step on Vertical field. Vertical position setpoint = -8mm.
141942007-02-07 17:12:08.908pduarte4.3228P feedback on Horizontal field and pre-programed step on Vertical field. Vertical position setpoint = -8mm.
141932007-02-07 17:06:50.388pduarte4.6228P feedback on Horizontal field and pre-programed 2 step on Vertical field. Vertical position setpoint = -8mm.
141922007-02-07 17:01:00.998pduarte4.32.428P feedback on Horizontal field and pre-programed 2 steps on Vertical field. Vertical position setpoint = -8mm.
141912007-02-07 16:52:08.862pduarte3.92.223P feedback on Horizontal field and pre-programed step on Vertical field. Vertical position setpoint = -8mm.
141902007-02-07 16:44:48.22pduarte4224P feedback on Horizontal field and pre-programed step on Vertical field. Vertical position setpoint = -5mm.
141892007-02-07 16:36:30.899pduarte3.92.425 P feedback on Horizontal field and pre-programed step on Vertical field. Vertical position setpoint = -5mm.
141882007-02-07 16:30:56.431pduarte3.5223P feedback on Horizontal field and pre-programed step on Vertical field. Vertical position setpoint = -10mm.
141872007-02-07 16:25:32.071pduarte42.115P feedback on Horizontal field and pre-programed step on Vertical field. Vertical position setpoint = 10mm.
141862007-02-07 16:18:27.048pduarte4.2228P feedback on Horizontal field.
141852007-02-07 16:12:12.471pduarte4.2228R = 0,2. ELCO=160V. PRECO OFF. P feedback on Vertical field and on Horizontal field.
141842007-02-07 16:02:14.456pduarte4.21.828P feedback on Horizontal field and on Vertical field.
141832007-02-07 15:55:01.963pduarte4.21.928P feedback on Horizontal field and pre-programed step on Vertical field from 11 to 26ms
141822007-02-07 15:45:27.986pduarte4.2228P feedback on Horizontal field and pre-programed 5 ms step on Vertical field from 11 to 18ms
141812007-02-07 15:39:04.967pduarte4.21.925 P feedback on Horizontal field and pre-programed 5 ms step on Vertical field from 9 to 14ms
141802007-02-07 15:31:22.153pduarte41.825P feedback on Horizontal field and pre-programed 5 ms step on Vertical field.
141792007-02-07 15:14:34.875pduarte3.5220R = 0,3. ELCO=160V. PRECO OFF. P feedback on Vertical field and on Horizontal field.