| Session aim | Machine conditioning. Tests with the new poloidal array of electric probes. | | Session day | 2009-01-12 | Operator | pduarte | | Session ID | ISTTOK_2009112_1 | Coordinator | pduarte |
|
Shot
|
Time
|
Operator
|
Iplasma(kA)
|
n(1018m-3)
|
Duration (ms)
|
Pre/post shot comments
|
| 20808 | 2009-01-12 16:41:17.10 | pduarte | 2.8 | 3 | 61 | 40 turns primary. R = 0,2ohm. ELCO = 200V. P=1,50x10^(-4)mbar. Pre-Programmed H and V field. Poloidal array tests. -50V on IONIC | | 20807 | 2009-01-12 16:24:50.80 | pduarte | 2.3 | 3 | 61 | 40 turns primary. R = 0,2ohm. ELCO = 200V. P=1,50x10^(-4)mbar. Pre-Programmed H and V field. Poloidal array tests. -50V on LANG | | 20806 | 2009-01-12 16:17:31.565 | pduarte | 2.2 | 2.9 | 61 | 40 turns primary. R = 0,2ohm. ELCO = 200V. P=1,50x10^(-4)mbar. Pre-Programmed H and V field. Poloidal array tests. -50V on LANG | | 20805 | 2009-01-12 16:09:29.384 | pduarte | 1.8 | 2.8 | 61 | 40 turns primary. R = 0,2ohm. ELCO = 200V. P=1,50x10^(-4)mbar. Pre-Programmed H and V field. Poloidal array tests. -50V on LANG | | 20804 | 2009-01-12 15:57:28.502 | pduarte | 1.6 | 2.8 | 61 | 40 turns primary. R = 0,2ohm. ELCO = 200V. P=1,50x10^(-4)mbar. Pre-Programmed H and V field. Poloidal array tests. -50V on LANG | | 20803 | 2009-01-12 15:47:38.604 | pduarte | 1.3 | 2.7 | 61 | 40 turns primary. R = 0,2ohm. ELCO = 200V. P=1,50x10^(-4)mbar. Pre-Programmed H and V field. Poloidal array tests. -50V on LANG | | 20802 | 2009-01-12 15:35:15.096 | pduarte | 1.3 | 2.9 | 61 | 40 turns primary. R = 0,2ohm. ELCO = 200V. P=1,40x10^(-4)mbar. Pre-Programmed H and V field. Poloidal array tests. -50V on RAKE | | 20801 | 2009-01-12 15:18:29.877 | pduarte | 1 | 2.7 | 51 | 40 turns primary. R = 0,2ohm. ELCO = 200V. P=1,30x10^(-4)mbar. Pre-Programmed H and V field. CIII on tech3 and OII on tech4. Poloidal array tests |
|